Nyíregyháza-Nagykálló line equipped with new constructions

By the end of November to early December, the construction of bus stops with garbage bins, benches and bicycle storage facilities, was completed and by March or April the power supply is expected to be built. Partners from Hungary have reviewed the possibility of the originally planned solar power generation and found that unfortunately it would not provide 100% security and would make the investment very costly, so it is necessary to involve the local power (electricity) company, which caused the schedule to slip. In March the digital passenger information panels (real-time boards) will also be available.